EnergyFairbanks · September 3, 2026

325 thousand to cut the diesel

A federal grant just pointed artificial intelligence at the most stubborn problem in rural Alaska power.

Daily Alaska staff · September 3, 2026 · Fairbanks

The U.S. Department of Energy awarded $325,000 to the University of Alaska Fairbanks for a project called AURORA-AI, which is building artificial intelligence tools for isolated rural power systems in Alaska. Total funding across all partners, including Cordova Electric Cooperative, Colorado State University and the National Laboratory of the Rockies, comes to about $725,000.

Many small Alaska communities run their own diesel generators with no connection to a larger grid, which means operators who misjudge nightly demand end up burning more diesel than they need to. UAF professor of electrical and computer engineering Richard Wies described the core problem this way: these communities do not have a bigger grid they are connected to, so they are completely isolated.

The AI tools are meant to forecast demand ahead of time, cut diesel use, and keep power steadier on these isolated grids. Phase one begins October 1 and runs nine months, with Cordova Electric Cooperative serving as the utility partner.

Phase two would require roughly $7 million in additional funding. If secured, the plan calls for deploying modular data centers of about 100 kilowatts each directly into community microgrid systems, small enough to sit in a single village while running on the same power system they are meant to help balance.

In this story

Questions people ask

How much money did UAF get for the diesel-cutting AI project?

The Department of Energy gave 325,000 to UAF, with total funding across all partners at about 725,000.

When does the AURORA-AI project start?

Phase one begins October 1 and runs for nine months.

Who are the partners on AURORA-AI?

Cordova Electric Cooperative is the utility partner, along with Colorado State University and the National Laboratory of the Rockies.

What would phase two of AURORA-AI involve?

Phase two would need roughly 7 million more and would put modular data centers of about 100 kilowatts each directly into community microgrid systems to cut diesel use.

Evidence

Sources

Claims and where they come from

  • The U.S. Department of Energy awarded $325,000 to the University of Alaska Fairbanks for the AURORA-AI project. · alaskasnewssource.com
  • Total funding across all partners is about $725,000. · alaskasnewssource.com
  • Phase one begins October 1 and runs nine months with Cordova Electric Cooperative as the utility partner. · alaskasnewssource.com
  • Phase two would require roughly $7 million more and envisions modular data centers of about 100 kilowatts each in community microgrids. · alaskasnewssource.com

Produced with AI assistance, narrated with Slav Lund's voice clone with his consent, and reviewed by a person before publishing. How we use AI →

Report an error in this story

Next in the feed

energyMat-Su · Just now

MEA power bills fall $5.32 a month starting Oct. 1 as fuel charge drops 8.4%

MEA's Cost of Power Adjustment falls from 10.195 to 9.34 cents per kWh, cutting a typical Mat-Su member's bill from $171.38 to $166.06.

  • MEA's Cost of Power Adjustment dropped from 10.195 cents to 9.34 cents per kilowatt-hour on Oct. 1, 2026, an 8.4 percent cut.
  • A typical 623-kWh monthly bill falls from about $171.38 to $166.06, a $5.32 decrease.
Read

energyAlaska · Just now

Rural Alaska heating fuel hits record $7.97 a gallon, state survey finds

A state survey of 100 rural Alaska communities found heating oil prices hit a record $7.97 a gallon, up 23% since January.

  • Rural Alaska heating fuel averaged $7.97 a gallon this summer, a record since 2005
  • Price is up 22.8% from January's $6.49 average
Read

energyFairbanks · Just now

Fairbanks power co-op's rolling-blackout plan takes effect Oct. 30

Golden Valley Electric can cut power 30 to 60 minutes at a time across 13 Interior zones when supply runs short; hospitals and emergency services are exempt.

  • GVEA's Controlled Load Shed Program takes effect Oct. 30 across 13 zones
  • Outages run 30 to 60 minutes per rotation and members still pay full price
Read