EnergyAnchorage · June 2, 2026

ai is eyeing the slope

A company wants to build one of America's biggest data centers in one of Alaska's most remote corners.

Daily Alaska staff · June 2, 2026 · Anchorage

A developer has proposed building one of the largest data centers in the country on Alaska's North Slope, a roughly 500 million dollar project that would cover about a square mile of land off the Dalton Highway, around 25 miles south of the region's main oil and gas infrastructure. The facility would run on its own natural gas power plant, fed by a newly built pipeline.

By some estimates, the facility could use more than double the natural gas that urban Alaska burns for electricity and heating combined. That consumption raises questions for Alaskans in Anchorage, the Mat-Su Valley, and Fairbanks who are already watching tight Cook Inlet gas supplies and rising energy costs.

The proposal comes as Alaska draws growing interest for large AI and data center development. Developers cite cheap land, abundant natural gas, and a cold climate that can handle much of the cooling these facilities need without the massive water use common in warmer regions.

The U.S. Air Force has separately invited companies to build data centers on military land near Anchorage and Fairbanks, including Joint Base Elmendorf-Richardson, Clear, and Eielson. A project of this scale on the North Slope could bring jobs to the region and new pressure to expand gas infrastructure there.

The state's public comment period on the preliminary decision for the North Slope project runs through June 15.

In this story

Questions people ask

Where on the North Slope would the data center go?

About one square mile off the Dalton Highway, roughly 25 miles south of the main oil and gas infrastructure.

How much would the North Slope data center cost?

Around 500 million dollars.

How would the data center get electricity?

From its own natural gas power plant fed by a newly built pipeline.

When can I comment on the data center proposal?

Public comment runs through June 15.

Evidence

Sources

Claims and where they come from

  • A developer has proposed a roughly 500 million dollar data center covering about a square mile on Alaska's North Slope. · alaskapublic.org
  • The facility would run on its own natural gas power plant fed by a newly built pipeline. · alaskapublic.org
  • By some estimates, the facility could use more than double the natural gas urban Alaska burns for electricity and heating combined. · alaskapublic.org
  • The U.S. Air Force has invited companies to build data centers on military land near Anchorage and Fairbanks, including Joint Base Elmendorf-Richardson, Clear, and Eielson. · alaskapublic.org
  • The state's public comment period on the preliminary decision is open through June 15. · alaskapublic.org

Produced with AI assistance, narrated with Slav Lund's voice clone with his consent, and reviewed by a person before publishing. How we use AI →

Report an error in this story

Next in the feed

energyMat-Su · Just now

MEA power bills fall $5.32 a month starting Oct. 1 as fuel charge drops 8.4%

MEA's Cost of Power Adjustment falls from 10.195 to 9.34 cents per kWh, cutting a typical Mat-Su member's bill from $171.38 to $166.06.

  • MEA's Cost of Power Adjustment dropped from 10.195 cents to 9.34 cents per kilowatt-hour on Oct. 1, 2026, an 8.4 percent cut.
  • A typical 623-kWh monthly bill falls from about $171.38 to $166.06, a $5.32 decrease.
Read

energyAlaska · Just now

Rural Alaska heating fuel hits record $7.97 a gallon, state survey finds

A state survey of 100 rural Alaska communities found heating oil prices hit a record $7.97 a gallon, up 23% since January.

  • Rural Alaska heating fuel averaged $7.97 a gallon this summer, a record since 2005
  • Price is up 22.8% from January's $6.49 average
Read

energyFairbanks · Just now

Fairbanks power co-op's rolling-blackout plan takes effect Oct. 30

Golden Valley Electric can cut power 30 to 60 minutes at a time across 13 Interior zones when supply runs short; hospitals and emergency services are exempt.

  • GVEA's Controlled Load Shed Program takes effect Oct. 30 across 13 zones
  • Outages run 30 to 60 minutes per rotation and members still pay full price
Read