EnergyAlaska · November 12, 2026

State approves 50-year lease for North Slope gas-fired data center, no grid tie-in

The Alaska Department of Natural Resources signed off on a 715-acre lease for the $500 million STAK Energy Campus near the Dalton Highway, promising up to 1,500 construction jobs but no power for Railbelt homes.

Daily Alaska staff · November 12, 2026 · Alaska

The Alaska Department of Natural Resources on Nov. 10 approved a 50-year land lease for a proposed computing data center on the North Slope, clearing the way for what would be Alaska's first large-scale commercial data center — but one that will not feed power into the electrical grid that serves most Alaskans.

The lease covers about 715 acres near Milepost 390 of the Dalton Highway, roughly 26 miles south of Deadhorse, according to the final finding and decision signed by DNR Commissioner John Crowther, as reported by Petroleum News. The project, called the STAK Energy Campus, will run on a natural gas power plant fueled by gas produced locally on the North Slope, and its buildings will sit on a raised gravel pad so Arctic air can cool the computing equipment instead of water, according to the agency's decision reported by the Alaska Beacon.

For readers in Anchorage, Wasilla or Fairbanks, the direct effect on a power bill is limited. DNR said the facility "would not be tied into the electrical grid that covers Alaska's Railbelt, though operators could sell power to customers in and around Prudhoe Bay," according to the Beacon's account of the decision. That means the multi-gigawatt plant will not lower — or raise — Railbelt electric rates, which cover the utilities most Southcentral and Interior households depend on.

Where the project does register for working families is jobs. DNR wrote that "construction is expected to require a peak workforce of up to 1,500 workers, while ongoing operations are anticipated to employ between 50 and 150 permanent personnel on rotating shifts." Initial site development is estimated to cost $500 million, and the broader buildout is expected to take six years, according to information STAK shared with DNR officials.

The state will collect rent on the land and a fee tied to how much electricity the data center produces and uses, with the exact amounts to be set after a market appraisal, DNR said. The agency argued the unusually long 50-year term matches the scale of the investment: a $500 million capital outlay, a multi-year construction buildout and "an operational life extending well beyond that buildout."

The approval followed a contentious public comment period. DNR extended the comment window earlier this year and received more than 1,200 responses, most opposed to the lease, according to the Beacon. The agency filed a 30-page response addressing concerns about noise, water use, greenhouse gas emissions and the company's ability to finance construction. DNR said questions about STAK's financing and the climate effects of the gas plant fall outside its authority to decide whether the lease serves the state's interest.

The facility will be visible from the Dalton Highway from about a mile away and will run a 1-to-3-gigawatt generation system that DNR acknowledged could produce "continuous turbine, cooling, and equipment noise" carrying for miles across flat tundra. The nearest inhabited town is 60 miles away, and DNR said the project's layout, including a supporting gas pipeline, is designed to avoid caribou habitat.

John Boyle, a former state natural resources commissioner under Gov. Mike Dunleavy who ran unsuccessfully for a state House seat in the Nov. 3 election, now serves as STAK Energy's chief strategy officer.

Tuesday's decision triggers a 20-day window during which opponents can ask DNR to reconsider, and the approval could still be challenged in court. If no challenge succeeds, STAK still needs a federal wetlands permit and a state air quality permit for the power plant before construction can begin — meaning ground has not yet broken on the project, and the six-year construction clock has not formally started.

The lease decision landed the same week DNR also approved a scaled-down, 6,800-acre land transfer to the Alaska Industrial Development and Export Authority near Houston in the Mat-Su, land that AIDEA has said could eventually support a separate data center or industrial project, though no specific tenant has been named.

For North Slope contractors and construction trades, the STAK project is a concrete hiring signal years out. For everyone else on the Railbelt grid, the campus changes little about electric bills — it is being built explicitly to stay off that grid.

In this story

Questions people ask

Where is the STAK Energy Campus located?

It sits on about 715 acres near Milepost 390 of the Dalton Highway, roughly 26 miles south of Deadhorse. That puts it well north of any Railbelt community, on the North Slope.

Will this data center affect my electric bill?

No. It runs on its own natural gas plant and won't tie into the grid that serves Anchorage, the Mat-Su and Fairbanks, so Railbelt rates stay the same either way.

How many jobs will the project create?

DNR says construction could need up to 1,500 workers at peak, with 50 to 150 permanent staff once it's running, a real hiring signal for North Slope contractors.

Has construction started on the data center?

Not yet. STAK still needs a federal wetlands permit and a state air quality permit before any ground breaks, and opponents have a 20-day window to ask DNR to reconsider.

Evidence

Sources

Claims and where they come from

Drafted with AI assistance from the sources listed and reviewed by a person before publishing. How we use AI →

Report an error in this story

Next in the feed

Alaska

Trump extends Jones Act fuel-shipping waiver 90 more days, through Feb. 14

Nov 15 · 2 min read

A federal waiver letting foreign-flagged tankers carry Gulf Coast fuel to Alaska will keep running into next year, but it covers no groceries, lumber or other freight.

▶ Watch
  • Waiver extended 90 more days, through Feb. 14, 2027, per CBP Cargo Systems Messaging Service #70435180
  • Extension takes effect midnight Eastern time Nov. 16, 2026
Kenai

Kenai hires more outside lawyers in fight over gas-storage space under its airport

Nov 15 · 4 min read

The city has added up to $30,000 for an outside law firm as it disputes the state's bid to lease underground storage space to ENSTAR, with public comments due Nov. 13 and winter gas supply on the line for Cook Inlet customers.

▶ Watch
  • Kenai City Council voted Oct. 21, 2026 to add up to $30,000 for outside law firm Pioneer Law LLC
  • State Division of Oil and Gas, led by director Haley Paine, issued a preliminary finding favoring ENSTAR over Hilcorp on Oct. 13
Mat-Su

Mat-Su Growth Outpaces the Grid: MEA's $65M Fishhook Project and a Record Storm Test the System

Nov 12 · 4 min read

As the Mat-Su Borough's population tops 117,000, the region's 85-year-old electric cooperative is racing to build new lines and substations while recovering from a December windstorm that cut power to more than 17,000 members.

▶ Watch
  • Mat-Su Borough population reached 117,412, up from 107,081 at the 2020 Census
  • MEA is building roughly 22 miles of new 115-kilovolt line and two substations along the Fishhook corridor